Hip braces glassed.

This morning I made the small fillets and got the fiberglass cloth on the the hip braces. After this cures, I’ll sand it smooth and give it a light coat of epoxy and then the hip braces will be done. Only a couple of steps left to go. After the hip braces are finished, I’ll do the hatch lips and finish the hatch covers. Then come the end pours. The end pours may actually be the steps that delay me more than any other so far, because they are completely weather dependent. I will need two dry, warmish, weekend days to take the kayak outside and stand it on end. It will then have to stand on end all day (probably strapped to a ladder) until the end pours cure enough that they won’t slump when I lay the kayak back into the horizontal position. But that’s it for the construction. After that, the entire kayak gets sanded. Then at least one more fill coat of epoxy to make things smooth. More sanding. Then spar varnish. After the kayak is varnished the deck rigging goes on, and the Ronan will be ready to paddle.

Port hip brace above. Starboard below.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.